Past Projects » 2017-18 Preventive Maintenance

COUNTYWIDE PREVENTIVE MAINTENANCE

County Project No. 820682

Fiscal Year 2017 to 2018


Preventative maintenance work will begin next week, July 17, 2018 and will continue through August 2, 2018. This project will resurface approximately 26 lane miles of roads in the First, Second, and Third Districts. The County of Santa Barbara Board of Supervisors awarded the contract for this project to California Pavement Maintenance Company, Inc. (CPM). The estimated construction cost is $1.7 million and funding is provided by State Senate Bill 1 (SB-1) funding and the County General Fund.


Construction hours are expected to occur Monday through Friday between 7 a.m. and 5 p.m. Drivers should be aware of reduced speed zones and increased traffic control when driving through the construction sites. For the safety of crew members and motoring public, please be observant of construction area signs and be prepared to stop when traveling through the work site. Public Works Department officials thank local residents and the traveling public for their patience and cooperation during the construction of this project.


For details regarding SB-1 Transportation Funding Projects in Santa Barbara County, please visit http://rebuildingca.ca.gov/.


For the official press release and complete street list and schedule, please see below:



PLEASE NOTE:
The project schedule is subject to change.

Due to critical fire weather conditions, the following roads listed below will be postponed to a later date.

07/25/18
San Antonio – from Via Los Santos to La Riata Ln
San Antonio – from La Riata Ln to Via Clarice
San Antonio – from Via Clarice to Hwy 154

07/26/18
Via Los Santos – from San Marcos Rd to Via Los Padres

07/27/18
Charlotte Ln – from SR 192 to South End
Exeter Spur – from Exeter Pl to Cheltenham Rd
Glen Albyn – from SR192 to Cheltenham Rd
Laurel Canyon Rd – Hwy 192 to North End
Selwyn Cir – from Cheltenham Rd to West End
Tunnel Rd – from 550’ N/O Montrose to North End